Try a sample exercise
A project costs Rs 100,000 now and generates Rs 60,000 at the end of each of the next two years. Given discount factors of 0.909 and 0.826, estimate the net present value.
Check your answer
Discount the two inflows to Rs 54,540 and Rs 49,560. Their total is Rs 104,100, giving an NPV of Rs 4,100 after the initial cost. The project clears the stated financial hurdle on these assumptions.