Try a sample exercise
Budgeted production was 800 units at Rs 14 each in variable cost. Actual output was 850 units and variable cost was Rs 12,200. Compare actual cost with the budget flexed to actual output.
Check your answer
The flexed budget is 850 × Rs 14 = Rs 11,900. Actual spending is Rs 300 higher, so the variable-cost variance is adverse. Comparing the two at the same output removes the effect of producing extra units.